Stratos Control Systems delivered a focused packaging line improvement project to stabilise servo performance, reduce minor stops, and improve fault visibility. By restructuring PLC logic and introducing better performance tracking and alarm prioritisation, the line achieved higher throughput and more confident day-to-day operation.

​

Automation Challenges for Engineers.webp

01

The Problem

The packaging line experienced servo synchronisation issues, frequent minor stops, poor fault history tracking, and inconsistent PLC structure.

 

Downtime during shift changeovers was impacting output targets and making fault response slower and less consistent than required for a high-throughput line.

02

Scope of Work

Phase 1 – Audit & Diagnostics

Stratos assessed the motion and control performance issues affecting reliability and throughput.

​

This included:

  • Servo motion diagnostics and synchronisation assessment

  • Review of PLC structure and fault handling approach

  • Assessment of fault history visibility and operator feedback

  • Identification of quick-win improvements and structural fixes

Improve Fault Finding and Maintenance.webp
Control System Replacement.webp

Phase 2 – Optimisation Strategy

A structured improvement plan was created to reduce minor stops and speed up fault response while improving maintainability.

​

The strategy included:

  • PLC code restructuring for consistency and clarity

  • Alarm prioritisation to support faster operator response

  • SCADA integration for performance and stop tracking

  • Improved fault history capture for repeat issues

Phase 3 – Implementation

Stratos implemented the updates and validated changes with site teams to ensure improvements were measurable and sustainable.

​

Implementation included:

  • Restructured PLC logic and fault routines

  • Alarm improvements aligned to line priorities

  • Performance tracking integration and visibility improvements

  • On-line testing, commissioning, and handover

Packaging SCADA & Line Monitoring.webp
Packaging HMI Development & Standardisation.webp

03

Platforms Used

The project utilised modern automation technologies, including:

​​

  • Allen Bradley PLC

  • FactoryTalk View SE

  • Servo motion control systems

04

Outcomes & Metrics

Key outcomes included:

​

  • 28% improvement in line throughput

  • 45% reduction in minor stop duration

  • Clearer fault visibility and improved fault history tracking

  • Improved operator confidence and faster response to issues

Looking at Factory Data.webp

Testimonial

“The structured approach to PLC logic and alarm management has materially improved our packaging line reliability.”

​

Maintenance Manager

Stratos Control Systems Ltd Control Panel Refurbishment Upgrade.webp

Frequently Asked Questions

Improve Packaging Line Reliability

Upgrade packaging automation with Stratos Control Systems to reduce stops, improve diagnostics, and drive measurable throughput gains with maintainable PLC standards.

bottom of page