Stratos Control Systems delivered a focused packaging line improvement project to stabilise servo performance, reduce minor stops, and improve fault visibility. By restructuring PLC logic and introducing better performance tracking and alarm prioritisation, the line achieved higher throughput and more confident day-to-day operation.
​

01
The Problem
The packaging line experienced servo synchronisation issues, frequent minor stops, poor fault history tracking, and inconsistent PLC structure.
Downtime during shift changeovers was impacting output targets and making fault response slower and less consistent than required for a high-throughput line.
02
Scope of Work
Phase 1 – Audit & Diagnostics
Stratos assessed the motion and control performance issues affecting reliability and throughput.
​
This included:
-
Servo motion diagnostics and synchronisation assessment
-
Review of PLC structure and fault handling approach
-
Assessment of fault history visibility and operator feedback
-
Identification of quick-win improvements and structural fixes


Phase 2 – Optimisation Strategy
A structured improvement plan was created to reduce minor stops and speed up fault response while improving maintainability.
​
The strategy included:
-
PLC code restructuring for consistency and clarity
-
Alarm prioritisation to support faster operator response
-
SCADA integration for performance and stop tracking
-
Improved fault history capture for repeat issues
Phase 3 – Implementation
Stratos implemented the updates and validated changes with site teams to ensure improvements were measurable and sustainable.
​
Implementation included:
-
Restructured PLC logic and fault routines
-
Alarm improvements aligned to line priorities
-
Performance tracking integration and visibility improvements
-
On-line testing, commissioning, and handover


03
Platforms Used
The project utilised modern automation technologies, including:
​​
-
Allen Bradley PLC
-
FactoryTalk View SE
-
Servo motion control systems
04
Outcomes & Metrics
Key outcomes included:
​
-
28% improvement in line throughput
-
45% reduction in minor stop duration
-
Clearer fault visibility and improved fault history tracking
-
Improved operator confidence and faster response to issues

Testimonial
“The structured approach to PLC logic and alarm management has materially improved our packaging line reliability.”
​
Maintenance Manager