Weetabix: modernising a legacy production line within a three-week shutdown

Three machines on a Weetabix production line ran on separate, ageing control systems out of manufacturer support. Stratos consolidated them onto one Allen-Bradley Compact GuardLogix 5380, replaced the servo drives and encoders, rebuilt the machine safety to PL d under ISO 13849-1:2023, and handed the line back within a three-week shutdown.

The original control rack and its input and output cards inside the machine control panel, before removal

PLC Upgrades & Migration Services UKPLC Programming ServicesMachine Control Systems UKFood & Beverage

Stratos Control Systems Ltd Corby

Controller
Compact GuardLogix 5380One controller for three machines
Safety
PL dISO 13849-1:2023, against PLr d
Shutdown
3 weeksLine handed back within it
Motion
Kinetix 5500842E CIP Motion encoders
Safety I/O
68 pointsPer machine, monitored
Network
EtherNet/IPStratix managed switching

Outcomes

  • Three control systems and three CPUs reduced to one controller: one platform to maintain, one program to support and one set of spares to hold
  • Line handed back within the planned three-week shutdown, on current and fully supported control equipment
  • Every safety function on the line assessed to ISO 13849-1:2023, achieving PL d against a required PL d
  • 68 dedicated, monitored safety I/O points per machine, diagnosable independently of the machine control system
  • Hardwired interlocking between machines removed, with those signals handled inside one controller
  • Obsolete PLC, drive and encoder equipment off the line, with spares availability and manufacturer support restored
  • Plant reporting maintained through the changeover with no loss of production data

The challenge

Three machines on the line each ran on a separate, ageing control system. Manufacturer support had ended, spare parts were increasingly difficult to source, and the machines relied on hardwired interlocks carried between them on dedicated multicore cabling. The safety functions had not been assessed against a performance level.

The servo drives and Stegmann line-shaft encoders offered no straightforward upgrade path. Weetabix needed the equipment replaced, the safety architecture consolidated and production-data collection kept running, without extending the planned three-week shutdown.

What we did

  • Consolidated three independent control systems onto one Allen-Bradley Compact GuardLogix 5380 controller, with 1769 Compact I/O distributed to each machine over EtherNet/IP. See PLC upgrades and migration.
  • Replaced the legacy drives, motors and line-shaft encoders with Kinetix 5500 servo drives, MPM series servo motors and Allen-Bradley 842E EtherNet/IP CIP Motion encoders, with bracketry and adapters made for the job.
  • Rewrote the three machine programs as one coordinated PLC application, and replaced the operator interfaces and their enclosures.
  • Designed and installed one machine safety system using POINT Guard safety I/O and power-to-lock guard locking, assessed to ISO 13849-1:2023.
  • Removed the hardwired signalling between machines and migrated production-data collection into the new system, so plant reporting carried on uninterrupted.

How the job ran

Line runningThree-week shutdown

  1. Survey and design

    A full investigation of the existing installation, with drawings mapping every existing conductor to its destination in the new system.

    Line running
  2. Early outages

    New guard switches and safety wiring installed on the machines and left isolated until commissioning, with the existing safety system fully in service. Bracketry trial-fitted, so any adjustment showed up weeks before it was needed.

    Line running
  3. Field infrastructure

    Cabling installed ahead of the changeover wherever the running line allowed it.

    Line running
  4. Changeover

    Control platform, drives, encoders and operator interfaces changed over, the new hardware designed to mount on the fixings the old equipment already used.

    Three-week shutdown
  5. Commissioning

    Safety validation, motion tuning, and confirmation of the data feeds to the site's reporting systems before handover.

    Three-week shutdown

The engineering effort went into the early outages. By the time the shutdown opened, the changeover was the only work left to do.

Equipment and standards

  • Allen-Bradley Compact GuardLogix 5380, SIL 2 / PL d
  • Allen-Bradley 1769 Compact I/O over EtherNet/IP
  • Allen-Bradley POINT Guard 1734 safety I/O
  • Allen-Bradley 700S-CF safety control relays
  • Allen-Bradley Kinetix 5500 servo drives
  • Allen-Bradley MPM servo motors
  • Allen-Bradley 842E EtherNet/IP CIP Motion encoders
  • Allen-Bradley PanelView Plus 7
  • Allen-Bradley Stratix managed switches
  • Wenglor power-to-lock guard locking
  • ISO 13849-1:2023

Photographs

Services involved

Ready to talk through your automation challenge?

Tell us what the system needs to do, or what it is doing that it should not. You will speak to an engineer, not an account manager.